Mira Catalina Elementary School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Mira Catalina Elementary School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 10.4 AC × 84942 per AC = 883397 883,397
Site Work Costs 883,397
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4520 SF × 395 per SF = 1785400 1,785,400
M2 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4529 SF × 395 per SF = 1788955 1,788,955
M3 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4520 SF × 395 per SF = 1785400 1,785,400
M4 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 3220 SF × 395 per SF = 1271900 1,271,900
Modernization Costs 6,631,655
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 7,515,052
Soft Project Costs 27.00 % of Hard Construction Costs 2,029,064
Hard Construction Cost + Soft Project Costs Subtotal 9,544,116
Escalation 5 years @ 4.50% per year = 24.62% 2,349,589
Overall Contingency   10.00% of total = 11.11% 1,321,523
Total Probable Phase One Plan Costs for
Mira Catalina Elementary School
13,215,228