Palos Verdes Peninsula High School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Palos Verdes Peninsula High School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 38 AC × 84942 per AC = 3227796 3,227,796
Site Work Costs 3,227,796
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 AB 300 Seismic Upgrade. Classroom building, new finishes, lighting, HVAC, electrical and structural upgrades 54680 SF × 395 per SF = 21598600 21,598,600
M2 AB 300 Seismic Upgrade. Classroom building, new finishes, lighting, HVAC, electrical and structural upgrades 54186 SF × 395 per SF = 21403470 21,403,470
Modernization Costs 43,002,070
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 46,229,866
Soft Project Costs 27.00 % of Hard Construction Costs 12,482,064
Hard Construction Cost + Soft Project Costs Subtotal 58,711,930
Escalation 5 years @ 4.50% per year = 24.62% 14,453,817
Overall Contingency   10.00% of total = 11.11% 8,129,527
Total Probable Phase One Plan Costs for
Palos Verdes Peninsula High School
81,295,274