Point Vicente Elementary School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Point Vicente Elementary School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace site utilities 10.4 AC × 84942 per AC = 883397 883,397
Site Work Costs 883,397
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Classroom building Media Center and Kids Club, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M2 Classroom and Specialty Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M3 Classroom and Specialty Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4820 SF × 395 per SF = 1903900 1,903,900
M4 Kindergarten building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 3032 SF × 395 per SF = 1193690 1,193,690
Modernization Costs 6,905,390
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 7,788,787
Soft Project Costs 27.00 % of Hard Construction Costs 2,102,972
Hard Construction Cost + Soft Project Costs Subtotal 9,891,759
Escalation 5 years @ 4.50% per year = 24.62% 2,435,173
Overall Contingency   10.00% of total = 11.11% 1,369,659
Total Probable Phase One Plan Costs for
Point Vicente Elementary School
13,696,591