Palos Verdes Intermediate School

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Palos Verdes Intermediate School – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
S1 Replace Site Utilities 27 AC × 84942 per AC = 2293434 2,293,434
Site Work Costs 2,293,434
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Classroom building, new finishes, lighting, HVAC, electrical and structural upgrades 12420 SF × 395 per SF = 4905900 4,905,900
M2 Classroom building, new finishes, lighting, HVAC, electrical and structural upgrades 11805 SF × 395 per SF = 4662975 4,662,975
M3 Lockers, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4966 SF × 395 per SF = 1961570 1,961,570
M4 Science and Media Center Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 8972 SF × 395 per SF = 3543940 3,543,940
M5 Classroom building, new finishes, lighting, HVAC, electrical and structural upgrades 11176 SF × 395 per SF = 4414520 4,414,520
Modernization Costs 19,488,905
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 21,782,339
Soft Project Costs 27.00 % of Hard Construction Costs 5,881,232
Hard Construction Cost + Soft Project Costs Subtotal 27,663,571
Escalation 5 years @ 4.50% per year = 24.62% 6,810,271
Overall Contingency   10.00% of total = 11.11% 3,830,427
Total Probable Phase One Plan Costs for
Palos Verdes Intermediate School
38,304,269