Valmonte-Sunrise Early Learning Academy

Estimate of Probable Costs

Summary of Estimate of Probable Costs

The following cost estimate is based on the plan for the Phase One Plan project scope (updated in 2024). Click on “Phase One Plan” in the site menu for a plan view of where these items are located on this site.

Phase One Plan Probable Costs

Valmonte-Sunrise Early Learning Academy – Phase One Plan

PI# Scope Description Quantity × Unit Cost = Cost Total Cost
Hard Construction Costs
Site Work
Site Work Costs 0
New Construction
New Construction Costs 0
Reconfiguration
Reconfiguration Costs 0
Modernization
M1 Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 2708 SF × 395 per SF = 1069660 1,069,660
M2 Classroom Building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 5406 SF × 395 per SF = 2135370 2,135,370
M3 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 5880 SF × 395 per SF = 2322600 2,322,600
M4 MPR, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 4769 SF × 395 per SF = 1883755 1,883,755
M5 Classroom building, new finishes, lighting, HVAC, electrical, low voltage, insulation and energy efficient windows. 8252 SF × 395 per SF = 3259540 3,259,540
Modernization Costs 10,670,925
Demolition
Demolition Costs 0
Miscellaneous
Miscellaneous Costs 0
Hard Construction Cost Subtotal 10,670,925
Soft Project Costs 27.00 % of Hard Construction Costs 2,881,150
Hard Construction Cost + Soft Project Costs Subtotal 13,552,075
Escalation 5 years @ 4.50% per year = 24.62% 3,336,276
Overall Contingency   10.00% of total = 11.11% 1,876,483
Total Probable Phase One Plan Costs for
Valmonte-Sunrise Early Learning Academy
18,764,834